Project Dictionary

09 Mayıs 2013 15476 0 PROJECT MANAGEMENT Fonksiyon360

Activity

The activity is the individual task required to complete a project. It is the smallest time and resource blocks handled by project management software. Activities are associated with each other by defining the premises. Activities are also called work packages, tasks and deliveries.

Activity Time

The duration of the activity specifies the length of time (hours, days, weeks, months) required to complete that activity. The workflow (associated activities identified by predecessors) can be defined without assigning durations to activities. Activities whose duration is 0 (zero) are called milestones (values ​​1-94) or hammocks (values ​​95-99).

Actual Dates

The actual dates are entered as the project progresses. These dates are the dates on which the gore activities actually started and finished for the planned dates.

Basic Project Timeline

The basic schedule is the fixed project timeline. It is a standard for measuring project performance. If there is a significant change in the scope of the project, the base chart is rebuilt.

Calendars

The project schedule lists the time intervals during which the activities or resources can be scheduled. A project generally has a fixed resume of the normal working week (Monday to Friday), but may have other calendars. Only one resource can be created for a specific calendar, a separate calendar for resources to be applied overtime ... Each calendar can be changed to specify their own vacation and extra work days. Sources and activities can be connected to any of the defined schedules.

Control

Auditing is the comparison of actual performance with planned performance, examining the differences and taking the appropriate corrective actions as necessary.

Critical Activity

Zero or nega- tive abundance (early end-early start = 0) activities. Displacement of these activities causes the project to be delayed.

Calculate the Timeline

The critical path method (CPM) is a modeling process that defines the timely completion of all critical activities of the project. The start and end dates of the activities in the project are calculated in two passes. In the first pass, early start and early end dates are calculated (forward-forward pass). The second transition calculates the late start and late end dates of the activities (backward-backward pass). The difference between the end date and the start date of each activity indicates the amount of that activity. For example, an activity with +2 abundance may start 2 days after the specified date, and does not delay the end date of this project. As explained in the Critical Activity, activities with a difference of 0 between the start and finish dates are critical activities. A delay in these activities affects the end date of the project.

Critical Path

There can be more than one critical path in a project. The critical path is the path of the activities that indicate the longest path required to complete the project. The delay to any activity on the critical path delays the completion of the project. There can be more than one critical path, depending on the time and the work flow.

Time

The length of time required to complete an activity is called the duration. The length of time is determined by user input or resource usage. Activities that have no duration or have a duration of 0 (zero) are called kilometer stone. Estimating the duration of future activities is very difficult. It is recommended to use the widest time periods by adding possible delays to the account.

Early Ending

The earliest calculated end date of an activity is defined as "early ending." It is based on the early start of the activity, which is based on the activity and the ending of the premise activity. (See Early Start ...)

Early Start

The date at which an activity can be calculated earliest is defined as "early start". It depends on the completion of all the preceding activities.

End Activity

The latest activity to be completed before the project is completed. This activity is not a predecessor to any other activity and has no successors.

Abundance

Abundance is the amount of time that an activity can be displaced without affecting the rest of the project. The calculation depends on the abundance type.

Free Abundance

It is the initial amount of time that activity can be shifted, which does not affect the end date of the subsequent activity. To calculate Free Abundance, Free Abundance = Early Start Date of Subsequent Activity - Early Start Date of that activity - Time of that Activity

Gantt Scheme

The Gantt diagram is a graphical representation of activity times. It is also called a bar chart.

Hammock

Groups to report a hammock, activities, milestones, or other hammocks. The number of milestones of a hamak is between 95 and 99. This allows 5 levels to recover. For example, two hammocks at level 95 can be combined into a hammock at level 96.

Histogram

Graphical representation of resource usage within a given time period. Resource usage is indicated by vertical colored bars. It is possible to identify overused or underused resources with this graphical representation.

Standby time

It is the time delay between the start or end of an activity and the start or end of its successor activities. As an example, after the foundation of a building has been laid, it is necessary to wait for 15 days for the foundation to start work on the ground floor. This 15 day period is called "lag".

Late Finish

Defines the date when an activity will be completed last without causing delays in a project. As indicated in the time program calculation, the late end dates are calculated by backward passes.

Late Start

It defines the date at which an activity will start at the latest without causing delays in a project. As indicated in the time program calculation, the late end dates are calculated by backward passes.

Milestones

Zero-duration activities are called milestones. In general, a phase / phase is completed.

Negative Abundance

Negative abundance indicates that activities must start before the end of their predecessor to catch the intended end date. Negative Abundance occurs when the difference between late dates and early dates (start or end) is negative (-). This may occur when certain constraints (target date of activity or end of project period) are added to the project.

Network Analysis

Network Analysis is the process of defining the early / late - start / end dates of project activities. This is done with forward and backward passes.

Network Diagram

Network Diagram is a graphical representation of the relationship with activity ranking and other activity (s). In graphical representations, the activity boxes are connected by one-way arrows (') to illustrate the precursors. The first activity is at the far left of the diagram, and the last activity is at the far right of the diagram.

Parallel Activities

Parallel activities are two or more activities that will take place at the same time. This allows the plant to be completed much faster than sequenced activities.

Way

The road is a series of interrelated activities. You can look at the Critical Path Method ..

Positive Abundance

Positive Abundance is the amount of time an activity can be delayed without affecting the completion date of the project. Positive abundance activity is not on the critical path and is called non-irritant activity. The difference between Early and Late dates (start or end) determines the amount of abundance.

Premise

An activity that needs to be completed (or partially completed) before the start of a given activity is called the "premise". All "Lead" and "Successive" relationships between project activities form the "Network".

Program Evaluation and Review Technique (PERT)

It is a project management technique that determines how much time it takes before a project is completed. The best (EI), worst (APP) and possible (O) completion time estimates for each activity are determined. These estimates are used to find the average completion time (OTZ).
OTZ = (EI + 4xO + EK) / 6
Standard Deviation = (EK-EI) / 6

Project

A temporary effort that produces an unmatched product, service, or result with a specific start and end date.

Source

The source is anything assigned to complete an activity. This source can be a device, human or material ...

Source Balancing

It allows to adjust the project schedule to balance the excessive consumption of daily resource usage. This usually happens when overloading resources. If there is an abundance of that activity, then in order to save that resource from overloading, the activity may be assigned a further schedule, and an additional resource may be assigned to the activity.

Time Programming

Time Programming is the process of determining the time at which project activities will take place based on their duration and premise activities.

Sort

Sorting is the sequence in which an activity takes place according to another activity. Ranking reveals dependencies and priorities among activities. Successive and Precedent relationships are developed in network format. This allows the workflow to be easily seen.

Startup Activity

The initial activity has no precedence. There is no other activity that needs to wait to get started.

Sub Project

It is a separate group of activities that make up their own projects as part of a large project. Subprojects can be aggregated into a single activity to hide details.

Succession

Successive, start, or finish is the activity that depends on the start or end of the activity. Look at the premise ...

Total Abundance

The amount of time the start date of an activity can be delayed so that the project does not delay the end date.
Total Abundance = Late End - Early Start - Time

Business Split / Break Structure

WBS is a hierarchical elaboration of the responsibilities and responsibilities of a project. At the top level in a project

Business Split / Break Structure

WBS is a hierarchical elaboration of the responsibilities and responsibilities of a project. It is developed by defining the top level work (s) in a project. These major business categories are divided into smaller pieces. The controllable smaller shredding operation is continued until the desired detail is reached. This lowest level of units is called "activity".

Workflow

The relationships of activities from the start to the end of a project are called workflows.

Workload

Workload is the amount of work units assigned to a resource in a given time period.

Business Units

Business Units is a measure of resources. As an example, people can measure gore to working hours and working days.

Zero Plenty

There is not much time between activities. Zero-volume activity is critical. Project completion is delayed if the completion times of critical activities are longer than planned.

Late Start - Early Start = 0

NO MORE COMMAND!

DO COMMAND

YORUM YAPABİLMEK İÇİN ÜYE GİRİŞİ YAPMANIZ GEREKMEKTEDİR.

OTHER REFERENCES

Akçansa
Türk Telekom
Türk Hava Yolları
Maliye Bakanlığı

OUR BLOG

Yukarı Çık
WE WILL CALL YOU